We are excited to partner with Vogel Bros. Building Co. in providing updates for our new K-8th Grade Building. Read below for their latest newsletter!
January Project Update
Vogel Bros. Building Co. is prioritizing the south half of the building where all the classrooms are located, We have completed the steel and concrete floors on the south side of the building. Our crews are currently working on interior wall framing and roofing on the south side as well. Meanwhile, the steel on the north side is almost complete. Interior mechanical, electrical and plumbing is underway in all areas of the new building.
NEXT STEPS
Pouring north side concrete floors in February
Roofing expected to be complete late February
Stone siding expected to begin in March
Glass will begin installation in April
Asphalt parking expected to begin in May
Pictured above: North Facing Conservatory Entrance
Pictured above: South Facing Front Entrance
Pictured above: Classrooms on the Main Level
Pictured above: Speciality classrooms, pictured here on the lower level is the science room, and the upper level room is our maker's space.
Pictured above: Gym
Did you know?
There is enough glass in the building to take up two NBA basketball courts.